The practice of project close-out finalizes all project activities completed
across all phases of the project to formally close the project and transfer
the completed or cancelled project as appropriate.
The purpose of project closeout is to assess the project, ensure completion,
and derive any lessons learned and best practices to be applied to future
projects.
However, in multi-phase projects, the close-out practice may be applied at
various stages of the project; upon deliverable completion, upon phase
completion, upon iteration completion, at designated times during the
project’s life, or at whatever other juncture represents a completed segment
of project work. Applying the close-out practice in this manner closes out
only the portion of the project scope and associated activities applicable
to that portion of the project.
The practice of project close-out consists of two main activity groups:
Administrative Closure – The administrative closure process defines
activities, interactions, and related roles and responsibilities of the
project team members and other stakeholders involved in executing the
administrative closure procedure for the projects.
Performing the administrative closure process includes integrated activities
to collect project records, analyze project success or failure, gather
lessons learned, transfer the project products or services to production
and/or operations, and archive project information for future use by the
organization. Among other activities administrative closure includes:
-
Confirming the project
has met all sponsor, customer, and stakeholder requirements
-
Verifying that all
deliverables have been delivered and accepted
-
Validating exit criteria
have been met
Contract Closure – Contract closure includes activities and
interactions needed to settle and close any contract agreements established
for the project, as well as those related to supporting the formal
administrative closure of the project.
Contract closure involves verification that all work has been completed
correctly and satisfactorily, updating of contract records to reflect final
results, and archiving information for future use. Among other activities
contract closure includes:
-
Confirming the project
has addressed the terms and conditions of the contracts
-
Confirming completion of
exit criteria for contract closure
-
Formally closing out all
contracts associated with the completed project
Project close-out should be anticipated and planned as early as possible in
the project lifecycle even though it is often the last major process of a
project’s life.
Verify Acceptance of Final Project Deliverables
The first step of the close-out process is the customer’s acceptance of the
final deliverables of the project. This is a critical and important step,
because it signifies that the customer agrees that the scope of the project
and its deliverables are complete and were delivered as agreed upon by all
parties. Acceptance is based upon the success criteria defined in the
initiating and planning phases of the project. This acceptance should be
formal, meaning that physical sign-offs should be obtained by the customer,
project sponsor, and the project steering committee, as appropriate.
Conduct Post-Project Assessment and Lessons Learned
In addition to communicating the closure of a project in writing, it is also
advisable to have a mechanism for group review & assessment of the project.
Lessons learned should draw on both positive experiences– good ideas that
improve project efficiency or save money, and negative experiences– lessons
learned only after an undesirable outcome has already occurred. Lessons
learned sessions are a valuable closure mechanism for team members,
regardless of the project’s outcome.
The lessons learned session is typically a meeting that includes:
-
Project team
-
Stakeholder representation including external project oversight,
auditors, and/or QA
-
Executive management
-
Maintenance and operations staff
-
Project support staff
Lessons learned and comments regarding project assessment should be
documented, presented, and openly discussed with the intent of eliminating
the occurrence of avoidable issues on future projects.
Conduct Post-Project Review and Evaluation
A post-project review provides a record of the history of a project. It
provides written documentation of the planned and actual budget, the
baseline and actual schedule, and documents recommendations for other
projects of similar size and scope.
Be certain to identify in the report the project successes, problems on the
project, and new ideas that were successful on the project. Make
recommendations on how these processes might be adapted for other projects.
Share the project’s success with other organizations. In the same way that
problem identifications can lead to improvements, successes must be shared
so they can be repeated. Where possible, successes should be translated into
procedures that will be followed by future projects.
Recognize and Celebrate Outstanding Project Work
Celebrating the success of completing a project with positive reinforcement
can be extremely rewarding for project teams. When a project is completed
successfully, be certain to provide some kind of recognition to the team. If
individuals are singled out for significant achievements, do not forget to
recognize the entire team as well.
Management may also want to express recognition of a successful team effort
by praising the team at a key meeting or a large gathering of staff. People
are proud to have senior management’s appreciation openly expressed, and
such recognition is a motivation to other projects to be successful.
Complete and Archiving Final Project Records
Historic project data is an important source of information to help improve
future projects. All records, both electronic and hard copy should be stored
according to record retention guidelines. The technical records will be
turned over to the personnel responsible for maintenance and operation of
the system or program after it has been deployed. The project archive
includes a description of the files being stored, the application used to
create the archived materials, the location where they are stored, and a
point of contact for further information.
Ensure Transfer of Knowledge
Once all the project information has been accumulated plan for knowledge
transfer where appropriate to those who will be responsible for continued
operations. Involve the project participants in the hand-off of
responsibility.